Justice A.A. Sathe Bombay HC AWARD MODIFIED A guarantee cashed in 2006 mustcome back, at lower interest
[ Bombay High Court ]

Bombay HC upholds order for MCGM to refund Rs 5.5 crore guarantee, trims post-award interest

Justice Aarti Sathe refused to set aside an arbitral award that sent back a bank guarantee cashed in August 2006. She held limitation was not a bar, but cut interest after the award from 12 to 10 percent.

On 25 August 2006 the Mumbai civic body cashed a Rs 5.5 crore bank guarantee while its contractor’s claim for more time was still before arbitrators. On 20 November the Bombay High Court refused to unsettle an award ordering the money returned with interest from that day. It trimmed only post-award interest, from 12 to 10 percent.

Justice Aarti Sathe decided a petition under Section 34 of the Arbitration and Conciliation Act, 1996, brought by the Municipal Corporation of Greater Mumbai (MCGM) in 2019. The respondent is Walter Bau AG, a German company in insolvency, acting through its insolvency administrator.

A guarantee cashed mid-arbitration

MCGM ran the Bombay Sewage Disposal Project, which included rehabilitation of the Bandra Collector Tunnel. The contractor’s predecessor completed the civil works on 18 July 2003, and MCGM issued the completion certificate four days later.

A dispute over extension of time followed. On 1 August 2003 the project engineer, Binnie Partners, told MCGM that liquidated damages of about Rs 5.5 crore could be recovered if no extension was granted, and advised it to hold security.

On 12 August 2003 MCGM asked for a bank guarantee of Rs 5,50,00,000 within seven days, failing which it would encash the performance guarantee. The contractor extended the guarantee under protest.

In September 2005 the extension-of-time dispute went to a three-member tribunal. While it was pending, MCGM invoked the guarantee by a letter of 21 August 2006, and Bank of India remitted Rs 5.5 crore to MCGM by pay order on 25 August 2006.

The bank had written on 23 August 2006 that the contractor wanted the guarantee extended by a year to 25 August 2007. MCGM refused on 24 August and asked the bank to pay.

From the 2011 award to the 2018 refund

That tribunal’s final award of 21 April 2011 granted the contractor 163 days of extension, from 5 February 2003 to 18 July 2003. The contractor had asked for the money back in 2009 and again in September 2011, and it invoked arbitration on 24 February 2014.

A new tribunal passed an award on 6 March 2018 directing MCGM to refund Rs 5.5 crore with interest at 12 percent a year. The contractor sought correction under Section 33, and on 11 September 2018 the interest start date was changed from 6 August 2013 to 25 August 2006.

MCGM filed its own Section 33 application on 5 October 2018. By a 2:1 majority the tribunal rejected it on 12 April 2019, and MCGM filed this petition on 19 September 2019.

Four attacks on the award

MCGM first said the claim was time-barred. The guarantee was cashed on 25 August 2006, the contractor knew it, and a claim raised almost nine years later was stale. Nothing, it said, stopped the contractor from arbitrating earlier.

It argued next that the award gave no adequate reasons, contrary to Section 31(3). It also said the correction of the interest date went beyond Section 33, relying on the Supreme Court’s decision in Gyan Prakash Arya v. Titan Industries.

It also argued that the tribunal, having corrected the date, left the words "from the date of claim" untouched. If interest ran from the claim, it said, the date should be 14 April 2015, when the claim was filed. It relied on the minority view on the tribunal.

Finally, it said 12 percent post-award interest was excessive and should be 6 to 8 percent. The project was public sewerage work, it said, and heavy interest would burden public funds.

The contractor’s reply

Walter Bau said earlier orders had already settled its standing and the limitation question. A Single Judge ruled on 31 October 2017, and a Division Bench affirmed on 22 December 2017, that it was the original contractor’s successor and the arbitration was in time.

It added that a Division Bench order of 26 August 2022 had finally settled the successor question, and that MCGM had not challenged it.

Its claim, it said, stayed inchoate until the extension dispute was decided. Its statement of claim had sought interest from 25 August 2006, so the 2013 date was a slip. It added that MCGM’s own Section 33 application came after the 30-day period.

On interest it relied on the Supreme Court’s ruling in Gayatri Balasamy v. ISG Novasoft. It called the contract commercial, whatever its public purpose, and said a wrongfully cashed guarantee drains a company’s liquidity at once.

Mr Yashodeep P. Deshmukh appeared for MCGM, and Senior Advocate Zal Andhyarujina for Walter Bau.

Why limitation did not bar the claim

Justice Sathe began by stressing that interference under Section 34 is limited. On limitation, she held the tribunal rightly relied on the 2017 orders in the parties’ other arbitration proceedings, which had treated the claim as in time.

When the guarantee was cashed on 25 August 2006, she noted, the extension dispute was undecided and no liability for liquidated damages had crystallised. The contractor’s right to a refund depended on how that dispute ended.

She rejected the argument that the contractor should have acted once the first tribunal turned down its interim application on 8 July 2010. That refusal did not oblige it to start separate proceedings while the underlying dispute was pending.

A Section 34 court does not re-weigh evidence, she added. The tribunal is the master of the facts, and its view stands unless it is arbitrary or perverse.

An award that gave its reasons

On Section 31(3), the court applied the Supreme Court’s test in Dyna Technologies. Reasons must be proper, intelligible and adequate, and the 2018 award met that test.

It had set out why the tribunal accepted the contractor’s standing and limitation case. Having held the claim inchoate while the extension dispute was pending, it logically found the August 2006 encashment unjustified.

MCGM, the judge said, had not even stated on what basis the award was unintelligible.

A date corrected, not rewritten

The Section 33 point took the longest. The tribunal had allowed the contractor’s application after hearing both sides, and MCGM raised no objection at that hearing, as the corrected award itself records.

The court then checked the nature of the error. The contractor’s statement of claim had asked for interest on Rs 5.5 crore from 25 August 2006, at 10 percent compounded annually, so the 2013 date was an inadvertent slip.

“did not constitute a substantive modification of the arbitral award” (para 51)

Justice Sathe held that the correction was a typographical one within Section 33(1)(a), and that reasons were not needed for it. Section 31 governs the form of an award, she said, while Section 33 deals with correcting slips.

She distinguished Gyan Prakash Arya, where the corrected gold rate was not in the original claim. She also distinguished Gujarat Water Supply v. Saryu Plastics, where simple interest had been changed to compound interest, a substantive matter.

MCGM’s own Section 33 application, seeking interest only from 14 April 2015, came after the 30-day period and was properly rejected by a reasoned majority.

The cases MCGM cited

The court found none of MCGM’s authorities apposite. Emmson Gulf, a Delhi High Court ruling, concerned an award that gave no reasons for refusing interest. This award was reasoned, and a Section 33 correction needs no separate reasons.

The Delhi ruling in Virender Khanna and Associates, on when a cause of action accrues, did not help on limitation, which the 2017 orders had settled. The Supreme Court’s Kamlesh Verma decision, on review, did not apply because the tribunal had not reviewed anything.

A Bombay ruling in TJSB Sahakari Bank held that a wrong interest rate need not sink a whole award. Here the rate for the arbitration period was right, and the post-award rate was adjusted.

Interest: 12 percent becomes 10

The court drew a line between interest before and after the award. Interest for the period of the arbitration lies in the tribunal’s discretion under Section 31(7)(a), and nothing barred it here, so that part stood.

For post-award interest she relied on Gayatri Balasamy, in which the Supreme Court held that courts have a limited power under Sections 34 and 37 to modify an award. That power covers severing a bad part from a good one, fixing clerical slips, and altering post-award interest in some circumstances.

Without it, the Supreme Court had observed, a court might have to set aside a whole award or order a fresh arbitration merely because the interest rate was wrong. Justice Sathe treated the present case as one for adjusting the rate.

Section 31(7)(b), as amended in 2016, sets that interest at two percent above the current rate on the date of the award. The award is dated 6 March 2018, when the prevalent rate was roughly 8.35 percent.

The tribunal had applied 12 percent. The court held the correct rate was 10 percent a year and modified the award to that extent.

“adopted a plausible view of the matter” (para 66)

Summing up, the judge held that MCGM had shown no ground for interference under Section 34 apart from post-award interest.

Order

The awards of 6 March 2018 and 11 September 2018 are modified only to reduce post-award interest from 12 to 10 percent a year. The remaining findings are not set aside, and the petition is disposed of with no order on costs.

Any amount deposited in the High Court is to be released in accordance with law within one month of the judgment being uploaded. All pending interim applications stand disposed of.

At MCGM’s request to approach a higher court, the judgment’s operation is stayed for four weeks from 20 November.