Justice A.A. Sathe Bombay HC AWARD UPHELD A contractor took payment, signed a no-claimcertificate, and sued for Rs 3.17 crore later
[ Bombay High Court ]

Bombay HC upholds award against Rs 3.17 crore claim on HCC: no-claim certificate was voluntary

Justice Aarti Sathe refused to disturb an arbitral award that dismissed a sub-contractor claim after the short-closure of an NH-34 work order. The arbitrator had found the signed certificate was not extracted by coercion, so the merits were never reached.

A sub-contractor on a national highway job signed a no-claim certificate in July 2011, took its final payment, and months later claimed Rs 3.17 crore in damages from Hindustan Construction Company Limited (HCC). On 20 November the Bombay High Court refused to disturb the arbitral award that threw the claim out.

Justice Aarti Sathe held that the sole arbitrator had correctly found the certificate was signed voluntarily, with no proof of coercion. That finding, she said, left no need to decide the merits of the damages claim.

The NH-34 job and the changed work order

The petitioner, Vishal Associates, is a proprietorship from Allahabad doing civil engineering work. On 14 July 2010 HCC issued it a letter of intent for work on NH-34 in West Bengal and at Sidpahadi in Jharkhand, with an estimated sub-contract value of Rs 10,99,50,000 and a one-year term.

The petitioner gave a performance bank guarantee of Rs 22 lakh. On 21 September 2010 HCC issued a work order that cut the completion period to six months and the estimated value to Rs 5.72 crore.

The petitioner said HCC officials pressed it to leave so another firm could take over. HCC said the petitioner raised seven running account bills from October 2010 and delayed the work.

Stone ban, joint inspection, a signed certificate

Work stood idle between March and July 2011 because of a Jharkhand government ban on stone mining. In April 2011 HCC asked for an extended guarantee of Rs 22 lakh, and the petitioner replied that Rs 10 lakh matched the work order value. On 12 July 2011 it gave a fresh guarantee of Rs 10 lakh.

A joint inspection followed around 15 July 2011. On 25 July 2011 the petitioner signed a “Work Completion and No-Claim Certificate”. It said it had been fully paid for the work done, had no balance due, and had given the certificate voluntarily and without compulsion.

The petitioner’s final bill of 16 August 2011 for Rs 12,70,145.20 was paid. On 21 September 2011 HCC released the Rs 10 lakh guarantee, and in December 2011 it paid Rs 34 lakh as the final amount.

The claim and the counterclaim

On 7 May 2012 the petitioner sent a demand notice claiming damages and compensation for delay in payment. HCC replied that all claims had been settled, citing the certificate.

The petitioner filed a statement of claim for Rs 3,17,46,000 on 27 February 2013. HCC counterclaimed Rs 2,48,82,687. The arbitrator, Justice Roshan Dalvi (Retd.), framed issues, with the first on whether the certificate was signed under coercion.

The award of 5 February 2020 held that the certificate was voluntary, dismissed the claim and imposed costs of Rs 1 lakh. The petitioner challenged it under Section 34 of the Arbitration and Conciliation Act, 1996.

What the petitioner argued

Mr Mutahhar Khan, for the petitioner, conceded that powers under Section 34 are limited. He argued that the arbitrator had tried only the certificate and never decided the actual claims.

He said the certificate covered only work executed and could not bar damages for short-closure or extra work. He also said the petitioner never received a copy and first saw it annexed to HCC’s statement of defence.

He argued that issues 2, 3 and 4 were left undecided without reasons, and relied on Mongia Realty and Buildwell Pvt. Ltd. against Manik Sethi, along with Ssangyong Engineering and Associate Builders.

HCC’s answer

Mr Ashish Kamat, Senior Advocate for HCC, said execution of the certificate was never in dispute. He pointed to the proprietor’s own evidence that he had been fully paid for the work done.

He said the petitioner had hidden the certificate in its demand notice, statement of claim and reply to the counterclaim, and had come with unclean hands. He cited Dalip Singh, Ramjas Foundation and other rulings on suppression.

A plea of coercion raised late

Justice Sathe began by saying that the dispute turned on the certificate. The arbitrator had framed issue one, she said, and the finding that it was voluntary could not be disturbed under Section 34.

She noted the arbitrator had reviewed the evidence. The proprietor admitted he was paid in full for the work done, and the arbitrator found he had never raised coercion in his notice, claim or reply to the counterclaim.

The arbitrator also recorded that the proprietor’s account shifted. He first said HCC typed the certificate and asked him to sign, then said that HCC officials had asked him to hand over a signed blank letterhead.

The court agreed the plea of coercion was an afterthought, first raised long after the certificate and after full payment. It held the petitioner had led no relevant evidence of how coercion was exercised.

Consideration for a settled account

The judge noted that by signing the certificate and securing release of its guarantee, the petitioner left HCC free to complete the work through another contractor. HCC in turn gave up its right to terminate, encash the guarantee and claim damages.

She held that this was good consideration for the petitioner’s receipt of what was due.

The certificate itself, she said, recorded full and final payment and said that nothing more was due. It also said it was given without compulsion, and it indemnified HCC against future claims.

Why issues two to four went undecided

On the missing findings, the judge relied on National Insurance Company Limited against Boghara Polyfab. Where a claimant says a discharge voucher was extracted by fraud or coercion, the tribunal decides that first, and if the discharge was voluntary, it refuses to examine the claim on merits.

That was the procedure the arbitrator had followed, the judge held. She distinguished Mongia Realty, noting that civil procedure rules do not strictly bind arbitrators.

She also relied on ONGC Mangalore Petrochemicals against ANS Constructions, which dealt with a belated plea of coercion after a no-claim certificate had been acted on.

No patent illegality, no re-weighing

Turning to Section 34, she said re-appreciation of evidence is not the court’s task. The arbitrator was the master of facts, and had taken a plausible view that the court could not replace with another.

She held that Ssangyong did not help the petitioner, since patent illegality must appear on the face of the record and go to the root of the matter. Associate Builders did not apply either, because the award did not rest on no evidence or ignore vital evidence.

The petitioner had been allowed to amend its petition in January 2024 to raise limitation under Section 34(3). When asked on 2 November 2026 why it was not argued, its counsel said the point was not pressed.

On HCC’s suppression argument, the judge said it need not be decided, because the arbitrator had in any case ruled on coercion. She had earlier said that the unclean hands argument “deserves to be accepted”, though the finding rested on the evidence.

Order

The High Court dismissed the Section 34 petition without interference. It disposed of any interim applications accordingly and made no order as to costs.

Any amount deposited in court is to be released within one month of the judgment being uploaded on the court’s website. Judgment was reserved on 8 October 2026 and pronounced on 20 November 2026.