Justice O.P. Shukla Delhi HC AWARD PARTLYSET ASIDE Extra cement, no clause to payfor it
[ Delhi High Court ]

Delhi High Court strikes Rs 3.17 crore award for extra cement used on DDA housing sites

Justice Om Prakash Shukla held that an arbitral tribunal rewrote a lump-sum contract when it made DDA pay for cement above 330 kg per cubic metre in M-30 concrete, while leaving the reading of the clashing clauses for M-25 and M-35 untouched.

The Delhi High Court has set aside part of two arbitral awards that made the Delhi Development Authority pay B.G. Shirke Constructions Technology Private Limited Rs 3,16,78,614 for extra cement in M-30 grade concrete.

Justice Om Prakash Shukla, in a common judgment on 23 November, held that the tribunal found no clause in the contract and no other legal basis for making DDA pay.

The contractor still keeps one finding. The court refused to disturb the tribunal's view that two clauses of the agreement clashed, which had defeated the authority's recovery claims for the other concrete grades.

Two clauses, two minimum quantities

DDA invited tenders to build 24,660 LIG and 7,130 EWS houses in Narela and Rohini using prefabricated technology. The work was split into two groups. Group-I covered 11,566 LIG and 2,275 EWS houses; Group-II covered 13,094 LIG and 4,855 EWS houses. Letters of award went to the contractor on 18 April 2013, and agreements were signed on 25 April 2013.

Clause 9.1.2 of each agreement said the minimum cement content for RCC would follow the CPWD Specifications, 2009, and IS:456. Those allow 330 kg to 500 kg per cubic metre, with the exact figure fixed through a design mix.

Clause 9.1.3 set a minimum of 360 kg per cubic metre for any grade of RCC. It also gave benchmarks of 410 kg for M-25 and 428 kg for M-35, below which DDA could recover money.

The contractor spotted the conflict before bidding. At the first pre-bid meeting it asked which figure governed, and DDA answered that the NIT provision would prevail. The second meeting produced the same answer.

During the work, DDA told the contractor to prepare design mixes with more than 330 kg of cement per cubic metre. The contractor said its rates were built on 330 kg and that it had been forced to spend more. DDA refused to pay, and the dispute went to arbitration.

What the tribunal awarded

The contractor invoked arbitration on 23 January 2015, and a tribunal of S.R. Pandey, P.S. Chadha and K.K. Varma was constituted on 28 June 2015. DDA objected to jurisdiction under Clause 8.2 of the Conditions of Contract, which sends discrepancies to the Work Advisory Board.

The tribunal rejected that objection and held the dispute arbitrable.

On the merits, the tribunal found a clear contradiction between Clauses 9.1.2 and 9.1.3. Because DDA drafted the tender, it applied contra proferentem and held that the CPWD figure of 330 kg applied to all grades. The recovery thresholds of 410 kg and 428 kg were treated as independent, so the contractor's claim for M-25 was rejected.

For M-30, the tribunal reasoned differently. Clause 9.1.3 named no recovery threshold for that grade, so nothing could be recovered, and the contractor's price was taken to rest on 330 kg. Since 410 kg had admittedly been used on DDA’s instructions, the extra 80 kg per cubic metre was payable.

The arithmetic ran as follows. The contractor’s final claim covered 65,997.11 cubic metres of M-30 concrete, giving 52,79,769 kg of excess cement. The tribunal priced it at Rs 6 per kg, the rate the contract used for recovery when less cement was used, which produced Rs 3,16,78,614 for work up to 30 June 2015.

The awards also ordered DDA to refund amounts already recovered for M-30 cement, and to pay Rs 6 per kg for excess cement used from 1 July 2015 onwards.

DDA and the contractor in court

Appearing through Ms. Chand Chopra and Mr. Punishk Handa for standing counsel Mr. Sanjay Katyal, DDA argued that the tribunal misread Clause 9.1.3, whose opening words covered any grade of RCC. The later mention of M-25 and M-35 only fixed recovery points.

Clause 9.1.2, it said, could not be read alone. The CPWD range of 330 to 500 kg left room for the agreement to set a higher minimum.

DDA also pointed to the pre-bid answers. The contractor had been told twice that the NIT provision would prevail, yet it bid and signed. It could not later call the requirement an employer-imposed variation.

The tribunal, DDA added, had awarded money without naming a clause, recording a breach, or assessing loss under Section 73 of the Indian Contract Act, 1872.

It relied on a string of decisions on the limits of a tribunal’s powers, including Associated Engineering Co. v. Government of Andhra Pradesh, Rajasthan State Mines & Minerals Ltd. v. Eastern Engineering Enterprises, DDA v. R.S. Sharma and Co., Indian Oil Corporation Ltd. v. Shree Ganesh Petroleum and Agmatel India (P) Ltd. v. Resoursys Telecom.

Mr. Rajiv Kapoor and Mr. Ashit Kapoor, appearing for the contractor with Mr. Ashok Patil, said DDA was raising a new ground. No objection had been taken before the tribunal that nothing could be paid for M-30 cement. The tribunal had considered both M-25 and M-30, rejected one claim and allowed part of the other.

They added that DDA had itself directed a design mix of 410 kg per cubic metre after ignoring the pre-bid queries. The tribunal’s reading of the clauses, they said, was interpretation and not a rewrite, and disclosed no patent illegality. In rejoinder, DDA said that no plea of quantum meruit under Section 70 had been made before the tribunal.

Limits of review under Section 34

Justice Shukla began with the limits of his own role. A court hearing a Section 34 petition does not sit in appeal over the award, and a tribunal’s reading of the contract stands even if another reading is possible.

That protection ends, he said, where a finding runs against the express terms of the contract. In SEAMEC Ltd. v. Oil India Ltd., the Supreme Court set aside an award because the tribunal ignored the rule that a contract is read as a whole.

He also cited GMR Ambala Chandigarh Expressways Pvt. Ltd. v. National Highways Authority of India, decided by the Delhi High Court, which bars a tribunal from adding to or subtracting from a commercial bargain.

“Thus, the permissible latitude in construing a contract cannot be stretched to the point of rewriting it.” (para 27)

M-25 and M-35: the tribunal’s view survives

The judge accepted that the two clauses were in tension on their face. Clause 9.1.2 pointed to a minimum of 330 kg, Clause 9.1.3 to 360 kg. DDA had been asked about it at both pre-bid meetings, so the issue was not an afterthought.

In his own view the clauses could have been read together, since 360 kg falls inside the CPWD range of 330 to 500 kg. But that did not make the tribunal’s contrary view implausible.

Finding the clauses ambiguous was a plausible reading, and interpreting a contract lies within the tribunal’s domain. The court left the findings for M-25 and M-35 alone.

Why M-30 stood on a different footing

For M-30 the court found the tribunal had gone wrong. Clause 9.1.2 refers only to M-25 and M-35, while Clause 9.1.3 sets 360 kg for any grade of RCC, which necessarily includes M-30. The tribunal never examined those words and simply carried its finding of inconsistency over to a grade that Clause 9.1.2 does not mention.

With no ambiguity for M-30, there was no occasion for contra proferentem. The court held that 330 kg could not be the minimum for M-30, as that fails to give effect to the express language of Clause 9.1.3. That finding was set aside.

No clause, no pleading, no payment

The court then asked a separate question: even if 330 kg was the baseline on which the contractor quoted, was it entitled to be paid for every kilogram above it? The agreement was a lump-sum contract, and the 410 kg DDA required sat within the CPWD range, which Paragraph 5.8.4.2 leaves to the design mix.

The tribunal’s only reasoning was that Clause 9.1.3 gave no recovery threshold for M-30. The judge said that may stop DDA from recovering money for M-30, but it does not oblige DDA to pay.

“The absence of a right to recover an amount from the Contractor does not, by itself, create a corresponding right in the Contractor to claim payment.” (para 41)

The contractor’s claim was not based on quantum meruit, and no such case was pleaded. The tribunal therefore had to identify a contractual provision or another legal basis. It cited none, and did not explain how DDA’s instruction became a variation carrying extra payment.

The amount appeared to rest on fairness or equity, the court said. A tribunal cannot apply that without express authority from the parties under Section 28(2) of the Act.

The court also faulted the use of the Rs 6 per kg rate. That figure comes from a clause for recovery when less cement is used, and nothing in it says the same rate is payable for excess. In effect, the tribunal applied a recovery rate in reverse and turned a penalty mechanism into a payment entitlement.

A contractor bidding on a lump-sum contract, the judge added, was expected to allow for the possibility that DDA might require more than the minimum cement. If it failed to price that in, DDA could not be made to carry the loss. No independent breach by DDA had been recorded either.

The court concluded that this was no longer a case of choosing one plausible interpretation over another. The tribunal had gone beyond the four corners of the agreement and created an entitlement with no contractual or legal footing, which made the award patently illegal to that extent.

Order

Both awards dated 22 May 2017 are set aside to the extent they held 330 kg per cubic metre to be the minimum for M-30 concrete and awarded Rs 3,16,78,614 for excess cement up to 30 June 2015.

The direction to pay Rs 6 per kg from 1 July 2015 also goes. So does the refund of recoveries on M-30 cement, to the extent it rested on the same reasoning, and the consequential interest.

The remaining findings of the awards are undisturbed. Both petitions are allowed in those terms, pending applications are disposed of, and there is no order as to costs.