Delhi High Court upholds Rs 15.8 crore award to BSCPL against NHAI for 374-day highway delay
Rejecting a Section 34 challenge by NHAI, Justice Om Prakash Shukla held that a contractor cannot repackage escalation as a prolongation claim, but can recover extended-stay costs from delays the employer itself caused.
The Delhi High Court has refused to disturb an arbitral award of about Rs 15.8 crore in favour of BSCPL Infrastructure Limited against the National Highways Authority of India. Justice Om Prakash Shukla dismissed NHAI’s petition under Section 34 of the Arbitration and Conciliation Act, 1996 on 23 November.
The award compensates the contractor for the 374 days by which a four-laning project on NH-26 in Madhya Pradesh overran. The ruling draws a line between two kinds of claims.
A contractor may not dress up a demand for higher escalation as a prolongation cost, the court said. It may, however, recover what it spent staying on site because of the employer’s defaults. The majority award under challenge is dated 13 May 2015.
A highway widened late
The contract, dated 12 April 2006, covered widening a two-lane stretch of NH-26 to four lanes and strengthening it, from km 255 to km 297 between Sagar and Rajmarg Chouraha. The contract price was Rs 189.63 crore.
Work began on 27 May 2006 and was due to finish on 26 November 2008. It was completed on 5 December 2009. The Engineer recommended an extension of time of 374 days, and NHAI approved it without any penalty or liquidated damages.
BSCPL then claimed its extra costs. A Dispute Adjudication Board held it was entitled to its claim and sent the calculations to the Engineer, who denied the claim.
The Board could not decide the matter afresh because its constitution lapsed after the defect liability period. BSCPL invoked arbitration on 5 February 2011.
What the tribunal awarded
BSCPL claimed Rs 40,33,65,879 across seven heads. The three-member tribunal, by a 2:1 majority, awarded roughly Rs 15.80 crore, with interest at 10 percent a year, compounded monthly, from 5 February 2011 until realisation.
Four heads succeeded. Claims 1A to 1D, for the extra cost of fuel and lubricants, cement, steel and bitumen during the extended period, brought Rs 4,38,36,642. Claim 2, for plant and equipment kept at site, brought Rs 4,55,10,280.
Claims 4 and 5, for site-office and head-office overheads, brought Rs 6,86,95,108. Claim 3, for financing charges, was rejected for want of proof of actual loss. Claims 6 and 7, for loss of promised bonus and of profit-earning capacity, failed for want of a sufficient contractual and evidentiary basis.
NHAI’s grounds against the award
Senior Advocate Ankur Mittal, for NHAI, argued that the award went beyond the contract and offended public policy. Under Clause 53.4 of the Conditions of Particular Application, he said, the tribunal could award only sums verifiable from contemporary records.
BSCPL, in his submission, gave no timely notice of its claims, kept no records open for inspection, and raised additional costs only after the extension was granted.
NHAI said the Engineer had repeatedly noted slow progress, poor planning and thin deployment of resources, with progress under 2 percent a month until July 2007. On materials, it said Clause 70 already gave price adjustment, so nothing more was due.
On plant and equipment, it argued that the tribunal used a wrong pro-rata method, that BSCPL relied on machines over five years old, and that some equipment was irrelevant to the work.
On overheads, NHAI pointed out that the hindered reaches were worth only about Rs 6.40 crore, against a site-overhead claim of over Rs 10 crore. It also said Clause 60.8 on interest did not apply to the sums awarded, and that the rate was excessive.
BSCPL’s answer
Mr Ajay Kumar Jha, for BSCPL, said Section 34 is not an appeal and the court cannot re-weigh evidence. The delay, he said, came from NHAI’s own defaults: late handover of sites, obstructions, a realignment at Bijora, shifting of electric poles, a work stoppage at Maharajpur and redesign of bridges.
BSCPL said it had flagged its intention to claim costs in its extension applications, and that Clause 53.4 allows a claim to be decided if contemporary records support it. Its figures, it said, were backed by vouchers and certificates from a chartered accountant.
It added that it deducted the Clause 70 price adjustment already received, and that the plant at site was jointly verified by the Engineer on 14 March 2009.
The narrow room under Section 34
The court began from the limits of its own jurisdiction.
“A petition under Section 34 is not an appeal, and the Court cannot reassess the evidence merely because it might prefer a different view of the contract or the facts.” (Para 47)
It cited Ssangyong Engineering v. NHAI for the rule that patent illegality must go to the root of the matter, and Sumitomo Heavy Industries v. ONGC for the rule that a plausible reading of the contract by the tribunal stands.
Who caused the 374 days
The court agreed that an extension of time does not by itself prove entitlement to every cost claimed, and that the absence of liquidated damages is not conclusive. But the tribunal had not rested on the extension alone.
It had examined the delay events, the Engineer’s own view that 185 days was reasonable for bridge works, and an internal NHAI headquarters communication of 25 January 2010.
NHAI had asked the court to take each hindrance separately and re-assess its effect. The court declined, since that would reopen findings of fact. Such findings can be disturbed only if unsupported by evidence, perverse or contrary to an express term of the contract.
The judge noted an earlier decision of the same court in NHAI v. Oriental Structural Engineers (2026 SCC OnLine Del 3540). It had reached a similar view on prolongation costs under a highway contract, including the reading of Clauses 6.4, 12.2 and 42.2 and the use of industry-based methods to quantify them.
Escalation is not prolongation
The sharpest legal question was whether Clause 70, the price-adjustment clause, shut out the claims for extra fuel, cement, steel and bitumen. NHAI relied on NHAI v. Progressive-MVR (JV), where the Supreme Court held that Sub-Clause 70.2 operates by its stated components and formulae.
The court accepted that principle. A contractor cannot use a prolongation label to get escalation on items the contract left out of the formula.
“A contractor cannot circumvent the agreed price-adjustment formula by simply describing an otherwise excluded escalation claim as a prolongation claim.” (Para 65)
But it held that the principle does not decide the case before it. A claim for further escalation on contract inputs is different from a claim for the cost of staying on site beyond the stipulated date because of employer-caused delay. The second kind has to be tested against Sub-Clauses 6.4, 12.2 and 42.2.
The judge then checked that the tribunal’s distinction was real. The claims covered only materials consumed in the 374-day extension, which the tribunal attributed wholly to NHAI’s defaults. The amounts were worked out on actual purchase and consumption.
Full credit was given for the Clause 70 adjustment already paid. No part of the claim touched the original contract period, for which the tribunal had treated the Clause 70 formula as exhaustive. The tribunal had also relied on NHAI v. HCC Ltd for reading Clause 70 together with the other clauses.
The court called this a permissible and plausible reading, and noted that NHAI had identified nothing to show double recovery.
Plant, equipment and overheads
On Claim 2, the tribunal had worked out an alternative figure of Rs 11,80,32,831, using a 20 percent machinery component, 374 days and a 15 percent deduction for mitigation. It did not award that sum. It gave only Rs 4,55,10,280, which it treated as BSCPL’s actual ownership costs.
The court found a rational basis in monthly machinery reports, invoices, inspection records, an auditor’s certificate and the Engineer’s joint verification. It also noted the contract barred removal of equipment without the Engineer’s written permission.
The Rs 6.40 crore value of the hindered reaches did not settle the point, it said, because the question was the cost of retaining equipment for the whole project.
The court drew on McDermott International v. Burn Standard for the rule that the method of assessing damages is mainly for the tribunal. It cited Batliboi Environmental Engineers v. Hindustan Petroleum as the limit: a method must be rationally supported and must not give a windfall or double recovery.
For overheads, the tribunal had applied the Ministry of Road Transport and Highways data book rates of 8 percent for road work and 25 percent for bridge work. It took a weighted average of 11.64 percent for the 374 days and cut the result by 15 percent for mitigation.
NHAI said those rates relate to project cost and not to duration. The court called this an objection to methodology that showed no arithmetic error, irrelevant cost base or double recovery.
The tribunal had not accepted BSCPL’s figures wholesale, the court said. Rejecting three heads of claim showed that it examined each head separately.
On notice and records, the court found the charge that no supporting material existed was not borne out. Disagreement with the weight the tribunal gave to records, it said, is a request to re-appreciate evidence.
Interest under Clause 60.8
The tribunal had awarded interest at 10 percent compounded monthly under Sub-Clause 60.8, from 5 February 2011. NHAI said the clause applies only to sums the Engineer had certified.
The court relied on this court’s ruling in NHAI v. Hindustan Construction Co. Ltd (2025:DHC:9222), which rejected a blanket objection of that kind and read the expression sums payable as covering amounts found due by a tribunal.
It added a caution. The date of invocation cannot automatically be treated as the contractual due date. Here, though, the claims had been submitted and rejected by the Engineer before arbitration began, so interest ran from the date of reference and not from when costs were incurred.
NHAI had pointed to no term of the contract or of the Appendix to Bid that barred this start date, or that set a different rate or method of compounding.
Order
The majority award dated 13 May 2015 is upheld. The amounts under Claims 1A to 1D, 2, 4 and 5, with interest as awarded by the tribunal, stay payable in accordance with the award.
The Section 34 petition, O.M.P. (COMM) 168/2016, is dismissed. Pending applications are disposed of, and there is no order as to costs.