Justice J.B. Pardiwala Justice K.V. Chandran Civil Appeal Who pays for a defaultingdeveloper's decade-long delay?
[ Supreme Court ]

Supreme Court Bars NOIDA from Saddling Homebuyers with Developer's Lease Penalty Charges

A Supreme Court bench of Justices J. B. Pardiwala and K. Vinod Chandran held that NOIDA's lease time-extension penalty charges cannot be imposed on innocent homebuyers or the resolution applicant.

The Supreme Court on 3 September 2026 set aside directions that would have treated NOIDA's lease time-extension charges as Corporate Insolvency Resolution Process (CIRP) costs, ruling that homebuyers and a Successful Resolution Applicant (SRA) cannot be penalised for a defaulting developer's failures. The bench, authored by Justice K. Vinod Chandran, directed NOIDA to waive the penalty charges altogether and dismissed NOIDA's cross-appeal seeking to extend those charges beyond the three-year lease period up to the tenth year. The ruling concerns two housing projects — Lotus Boulevard in Sector 100 and Lotus Panache in Sector 110, Noida — developed by M/s Granite Gate Properties Private Limited, which was later declared a Corporate Debtor under the insolvency process.

The Dispute: Two Stalled Projects and a Decade of Delay

Granite Gate Properties took two plots on perpetual lease from NOIDA at a high premium and advertised two apartment complexes under the Lotus brand. The projects were to have been completed by 2016. They were not. The developer ran into financial difficulties and was declared a Corporate Debtor. A Committee of Creditors (CoC) was constituted, composed entirely of homebuyers who qualified as a class of Financial Creditors.

During the CIRP period, homebuyers pooled their own resources — advance payments of the balance sale consideration — and carried on construction as a going concern under a CoC-approved “Pool and Build” mechanism. A Resolution Plan submitted by M/s SMV Agencies Private Limited was eventually approved, making it the SRA. Despite all of this, as of the date of the Supreme Court hearing, homebuyers remained without possession — a decade after the promised completion date.

NOIDA added a further complication. On 16 October 2024, it sealed three towers of Lotus Panache until the dispute over time-extension charges was resolved. Those charges, levied for delay in completing construction within the lease timeline, had accumulated across multiple years.

What the NCLAT Had Directed

Several Interlocutory Applications were filed before the NCLT, the adjudicating authority, including one by the Resolution Professional to approve the Resolution Plan. From the directions that followed, the Authorised Representative of the homebuyers (AR) and NOIDA each filed appeals before the National Company Law Appellate Tribunal (NCLAT).

The NCLAT directed that time-extension charges under both lease deeds be treated as CIRP costs, but limited this to the maximum three-year extension period stipulated in the original lease deeds. NOIDA was dissatisfied and appealed to the Supreme Court, contending that its office order dated 18 October 2019 — read with an earlier order dated 18 June 2015 — introduced a policy extending time-extension charges from year four through year ten, at rates of 7%, 8%, 9%, and 10% for the first four additional years and 1% of the total premium per year thereafter, with cancellation of the lease after the tenth year. NOIDA argued these too must be included as CIRP costs.

The AR, representing homebuyers, contested the opposite end: that any time-extension charges should not form CIRP costs at all, since they were penal in nature, arose from the developer's default, and were not incurred by the Resolution Professional nor connected to continuation of the project under Section 5(13)(c) of the relevant regulations. The AR argued that only charges from the insolvency commencement date of 10 January 2019 could even arguably be included.

The Court's Reasoning: Welfare Purpose Cannot be Divorced from Penalty Design

The Court examined the lease deed produced on record and traced NOIDA's underlying statutory purpose. The land had been acquired under the Land Acquisition Act, 1894 for development by NOIDA to set up an urban and industrial township. The Court found that the authority's entry into lease agreements served the broader goal of promoting industrial and commercial enterprises and providing housing in multi-storeyed buildings — a welfare measure alongside revenue generation.

On the original lease structure, the time-extension charges were set at 4%, 5%, and 6% for the first, second, and third years of delay respectively, with cancellation and resumption of the property to NOIDA as the only consequence after three years. The new policy introduced charges stretching to the tenth year. The Court characterised both as penalty provisions — designed to penalise a defaulting developer and act as a deterrent against time overruns.

The Court said the essential purpose of development would fail if NOIDA applied default charges in a situation where the defaulting developer was entirely out of the picture. The project was stalled not because of the homebuyers or the SRA, but because of the Corporate Debtor's failure. Homebuyers had already invested their savings, pooled additional resources during the CIRP to keep construction alive, and accepted a Resolution Plan. Imposing penalty charges on them and the SRA for the developer's past sins, the Court found, was impermissible.

The Court further noted that a local authority like NOIDA is concerned essentially with the development of the area under its control and cannot be driven purely by a profit motive. When development fructifies, taxes and duties from housing and commercial activity flow back into infrastructure spending. Penalising the very mechanism designed to complete an incomplete housing project cut against that purpose.

The SRA's counsel had additionally flagged, without prejudice, that the Resolution Plan capped contingent protection at the overlap period balance and recorded that any cost above Rs. 3 crores — unless specifically adjudicated as CIRP costs by a binding judicial pronouncement — would first be recovered from allottees of Towers 17, 18, and 19 of Lotus Panache as a super area charge. The Court's ruling removes that contingency entirely for NOIDA's penalty charges.

The Specific Rejection of NOIDA's Expanded Claim

NOIDA's appeal in Civil Appeal No. 4207 of 2026 sought to have the post-three-year charges under its 2019 office order included as CIRP costs as well. The Court dismissed this outright. The original lease deed contained no provision beyond three years other than cancellation. NOIDA's attempt to bring in charges for years four through ten under a subsequently issued office order, and to saddle the resolution process with those amounts, found no acceptance.

The Court's view was that neither the SRA nor the homebuyers caused the delay that generated these charges. Treating them as CIRP costs would effectively make the creditors — the very persons the insolvency process exists to protect in this case — bear the financial consequences of the original developer's default.

Order

The Court set aside the NCLAT's direction to consider time-extension charges as CIRP costs and modified the impugned order to that extent. It held that the penalty charges imposed by NOIDA for delay cannot be validly imposed on the SRA and the homebuyers in the peculiar facts of this case, and directed NOIDA to waive them.

Civil Appeal No. 3132 of 2026, filed by the Authorised Representative of the homebuyers, was allowed. Civil Appeal No. 4207 of 2026, filed by NOIDA, was dismissed. All pending applications were disposed of.