Justice J.B. Pardiwala Justice K.V. Chandran Civil Appeal Power flowed through the loops,so the loops get paid
[ Supreme Court ]

Generator that delayed its own line must pay for Power Grid LILOs it used, Supreme Court holds

Justice J.B. Pardiwala and Justice K. Vinod Chandran held that a generator without its own dedicated line pays for Power Grid LILOs from January 2015 to October 2016.

For almost 22 months, power from a new Tamil Nadu plant ran through two short loops of transmission line at the Tuticorin Pooling Station. The plant and the State distribution company said the loops were never used, so nobody should pay for them. On 18 November the Supreme Court held that the generator’s own admissions ended that argument.

A bench of Justice J.B. Pardiwala and Justice K. Vinod Chandran allowed the appeals of Power Grid Corporation of India Limited (PGCIL).

Justice Vinod Chandran wrote the judgment. It set aside two orders of the Appellate Tribunal for Electricity (APTEL) and restored the order of the Central Electricity Regulatory Commission (CERC).

Two loops on the Tuticorin–Madurai line

The dispute is about two LILOs, short for Line-In Line-Out or Loop-In Loop-Out. They intercept the two circuits of the Tuticorin JV–Madurai 400 kV line at the Tuticorin Pooling Station, so that power is routed through the station and sent back onto the line. The first was commissioned on 4 January 2015 and the second on 8 January 2015.

PGCIL, the Central Transmission Utility, claimed transmission tariff for both. The claim ran from the commissioning dates to 27 October 2016, the day the generator’s own dedicated transmission line (DTL) reached the pooling station. The generator is Moxie Power Generation Limited, formerly Coastal Energen Private Limited.

The Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) buys the power. Generation, transmission, supply and end use were all admitted. The only question was whether the LILOs were operational and used.

What each side told the court

Mr Ramji Srinivasan, Senior Counsel for PGCIL, said the CERC had approved both commercial operation dates on the strength of a trial-operation certificate from the Regional Load Despatch Centre and a Central Electricity Authority certificate. APTEL, he argued, had invented a test of “beneficial use” that transmission regulation does not know.

He added that open access charges and transmission tariff are different things. Open access charges are operational charges worked out by the National Load Despatch Centre. Tariff services the capital cost, return on equity, interest and depreciation of the asset.

Mr Sajan Poovayya, Senior Counsel for Moxie, said the LILOs were never put to use. He said power would have flowed seamlessly even without them, and that PGCIL’s upstream line from Tuticorin to Salem came into operation only on 13 November 2016.

His second point was statutory. Under Regulation 4(3)(ii) of the CERC Tariff Regulations, 2014, a generator is liable only once a commercial operation date has been declared in the prescribed way. Ms Vrinda Bhandari, Advocate-on-Record for TANGEDCO, adopted those arguments and relied on paragraph 72 of the CERC order.

A 50:50 order and a reversal

The CERC accepted the commercial operation dates of 4 and 8 January 2015. The scheduled date was 11 April 2014, and the judgment records over-runs of 8 months 23 days and 8 months 27 days for the two assets.

The CERC did not condone the delay. It left PGCIL free to give documentary proof of its reasons at truing-up.

On liability, the CERC relied on the minutes of the 30th Standing Committee meeting of 5 May 2010. It directed that the generators pay transmission charges for the two assets until their DTL was commissioned.

Half of the LILO charges were to go into the Point of Connection pool and the other half to the generator. The generator, though a party, did not appear before the CERC.

APTEL framed five issues and considered Non-PoC charges of Rs 15,43,26,909 for the period. It agreed that the LILOs were a permanent part of the plan. It held, however, that no power flowed through them and that the procedure under Regulation 4(3)(ii) had not been followed.

On review, APTEL remanded the question of the commercial operation date to the CERC. Both orders were before the Supreme Court.

Three questions the bench framed

The court framed three questions of law. The first asked whether PGCIL could include the LILOs in its tariff. The second asked whether APTEL had misread Regulation 4(3)(ii). The third was about who pays for the gap:

“Whether the delay in construction of the DTL would enable the liability for the period between 04.01.2015/08.01.2015 and 27.10.2016 to be mulcted on the generating company” (para 20)

How the court maps the grid

Regulation 4(3)(ii) speaks of the “upstream” and “downstream” transmission systems without defining either. The bench went to the Electricity Act, 2003 to fill the gap.

Under Section 10, a generating company must establish its generating station, tie-lines, sub-stations and dedicated transmission lines. The DTL is therefore the generator’s obligation.

The court divided transmission into three stages. The DTL carries power from the generating station to the Central Transmission Utility’s lines.

The CTU’s lines, which include LILOs and pooling stations, carry it to the distribution licensee. The licensee’s own system then supplies consumers.

On that scheme, the upstream system is the inter-State network built by the CTU. The downstream system is the one built by the distribution licensee within the State.

A pooling station, the bench noted, is the hub that collects power from several generators and aggregates it for the main grid. Tuticorin was to take power from three sources.

Why the loops were not idle

The generator’s main factual plea was that electricity takes the path of least resistance and would have gone straight to Madurai. The court accepted the principle but found it wrong on these facts. Power evacuated through the generator’s temporary LILO met PGCIL’s permanent LILO and was diverted through the pooling station.

The bench then turned the generator’s own pleadings against it. In its appeal before APTEL the company had said it was using the Tuticorin Pooling Station under short-term and medium-term open access.

It had also cited a medium-term grant of 558 MW from 1 July 2015 to 30 June 2018. Its only complaint was about sharing the charge. The court called that an admission of use.

The record of the planning meetings pointed the same way. The 29th Standing Committee meeting of 27 August 2009 had not planned LILOs at the pooling station. The 30th, on 5 May 2010, added them because Tuticorin JV could spare only one bay.

The Bulk Power Transmission Agreement of 24 February 2010, as replaced on 8 September 2011, listed the LILO of both circuits.

On those facts the court rejected the idea that the delayed Tuticorin–Salem line made the loops redundant. That line was never needed to move the generator’s power, which went out through the Tuticorin JV–Madurai line. Its holding on this point was short:

“The beneficial use is hence clearly established.” (para 37)

What Regulation 4(3)(ii) actually covers

The bench read the regulation narrowly. It applies only when a transmission element is kept out of regular service for reasons not attributable to the transmission licensee, because the generating station or the upstream or downstream system was late. In that case the licensee applies to the CERC for approval of the date of commercial operation.

Here, the court said, nothing prevented transmission from the day generation began. Regular service means putting an element into use after successful trial operation and a certificate from the Regional Load Despatch Centre. The CERC had applied that definition on the certificates PGCIL filed by affidavit on 12 May 2016, along with the 1x80 MVAR bus reactor at the station.

The commercial operation dates therefore needed no re-determination under the regulation. The court added that the delay in operationalising the DTL assumed significance once the LILOs were working as the upstream path.

Who bears the gap

All parties relied on Power Grid Corporation of India Limited v. Madhya Pradesh Power Transmission Company Limited, reported at (2025) 8 SCC 705. There the delay was the distribution licensee’s.

The CERC had made that licensee pay transmission charges from the declared commercial operation date. The judgment notes that Justice Pardiwala wrote that decision.

The court recalled that case’s reasoning on the CERC’s powers. Section 79 orders may be passed even without a regulation under Section 178, provided they stay within existing regulations. It also cited PTC India Limited and Energy Watchdog on the same point.

It held that the dictum “squarely applies” here. The generator failed to build and operate its DTL in time, so the liability the CERC placed on it between the commercial operation date of the LILOs and the commissioning of the DTL was justified.

Where APTEL went wrong

The bench said APTEL accepted the LILOs as a permanent part of the plan and then found their use unproved, despite the generator’s admission. It also noted that the generator had raised no objection in the planning meetings and had not taken part in the tariff proceedings.

APTEL had leaned on paragraph 72 of the CERC order, the source of “beneficial use”. The Supreme Court read that paragraph as a record of TANGEDCO’s contentions, not a finding. Paragraphs 73 to 77 of the CERC order posed the liability question and placed it on the generator.

The court also noted that APTEL itself had recorded PGCIL’s complaint about TANGEDCO’s stands. TANGEDCO had argued that no transmission charges were due despite use of the LILOs, and also that the LILOs were never used at all.

Order

The court answered the first question of law in the affirmative. The two LILOs are includable in the transmission tariff, as the CERC found, from 4 January 2015 until the DTL was established on 27 October 2016, as non-PoC.

The second was answered in the negative, as APTEL’s reading on the commercial operation date was erroneous. The third was answered in the affirmative.

The APTEL orders in both appeals, one in the original proceedings and one on review, were set aside. The CERC order was restored, and pending applications were disposed of.