Land handed over for a sub-station in 1991 never vested in the State, Supreme Court holds
A Bench of Justice Satish Chandra Sharma and Justice Nongmeikapam Kotiswar Singh upholds fresh acquisition under the 2013 Act and refuses to cap the cost at the old rate.
In 1990, an electricity board asked landowners in Tenali to let it start building a sub-station on their land while the paperwork caught up. The owners agreed, on condition that compensation would follow under the Land Acquisition Act, 1894. The paperwork never caught up, and the sub-station has run on that land ever since.
On 27 November, the Supreme Court held that the land never vested in the State. The acquisition lapsed under Section 11-A, and the owners remain owners.
A Bench of Justice Satish Chandra Sharma and Justice Nongmeikapam Kotiswar Singh dismissed the appeals of Transmission Corporation of Andhra Pradesh Limited, the Board’s successor. It upheld a direction for fresh acquisition under current law. Justice Kotiswar Singh wrote the reportable judgment.
A sub-station built on consent
The owners held about four acres in Tenali Town, Guntur District. On 7 January 1990, the Andhra Pradesh State Electricity Board decided to build a 132 KV/33 KV sub-station and staff quarters there. By a letter of 25 September 1990, its Divisional Engineer asked the owners to hand over the sites while acquisition was finalised.
He promised that the amount fixed by the Revenue authorities would be deposited with the Revenue Divisional Officer.
The owners consented on 5 October 1990, keeping the right to take compensation under protest and to seek a reference to court. They said the Board must abide by the Act for compensation, solatium and interest, whether or not Gazette publication and other procedures were gone through.
The Board took about 2.95 acres on 22 January 1991 and about 1.12 acres on 8 July 1991, each time “subject to final handing over by Revenue Authorities”. The Corporation says the sub-station has been operational since 1993.
Two notifications and no award
The formal process came after the possession. A Section 4(1) notification for Stage-I was published on 30 September 1991, with a Section 6 declaration on 15 October 1992. For Stage-II, the Section 4(1) notification came on 15 October 1992 and the declaration on 12 November 1993.
Neither notification invoked the urgency provisions of Section 17. Both appointed an officer for the Section 5-A enquiry. The Board deposited Rs 1,75,000 for Stage-II and nothing for Stage-I.
The owners appeared at the award enquiry in December 1993 and January 1994 and claimed Rs 600 to Rs 800 per square yard. No award followed, and talks failed. On 12 July 1996, the Board offered between Rs 33 lakh and Rs 35 lakh per acre, and the owners wanted Rs 50,62,500.
Meanwhile, the Section 11-A period ran out. On 9 January 1996, the Board’s own Executive Engineer wrote that both stages had lapsed and asked for fresh proposals. On 19 February 1996, the Revenue Divisional Officer agreed and asked for a deposit of Rs 5,11,09,900. The Board thought it excessive and paid nothing.
From the Single Judge to this Court
The owners filed Writ Petition No. 33513 of 1997 on 15 December 1997, seeking compensation on the footing that the notifications had lapsed. The Board and the Revenue Divisional Officer admitted the lapse in their counter affidavits. The Board also offered to shift the sub-station and return the land. The owners declined.
On 8 September 1998, the Single Judge held that possession taken with consent before the notifications was to be treated as possession under Section 17(1). The land therefore vested in the State and Section 11-A did not apply.
Awards 11 and 12 of 1999 followed on 15 September 1999, at Rs 60 per square yard with solatium, additional market value and interest, totalling Rs 40,00,095. Four owners took their shares under protest, and the rest was deposited in the District Judge’s court at Guntur.
On 19 April 2018, a Division Bench of the then High Court at Hyderabad allowed the owners’ writ appeal. Relying on R.L. Jain v. DDA, (2004) 4 SCC 79, it held that possession taken before any step under the Act was outside the Act.
It held the proceedings lapsed, called the awards non est, and directed fresh acquisition within three months.
This Court issued notice on 3 July 2019 and stayed that judgment.
What the Corporation argued
Additional Solicitor General Aishwarya Bhati appeared for the Corporation. She said the owners handed over possession voluntarily, “irrespective of the formalities, technicalities etc.”, and that Section 4 notice was substantially complied with, as the owners knew of the acquisition.
In substance, she argued, the acquisition was one under Section 17, which allows urgent acquisition for an electricity system. Possession came after notice and with consent, so the land vested and Section 11-A had no role.
She relied on Satendra Prasad Jain v. State of U.P. and Delhi Airtech Services (P) Ltd. v. State of U.P., (2024) 17 SCC 610.
The admissions of lapse were concessions on a point of law, she said, and could not bind the State.
The writ petition was belated, the owners were estopped after taking compensation, and their higher claims rested on sham family sales. Without prejudice, fresh acquisition of a critical utility site would cost over Rs 150 crore, so the relief should be moulded.
What the landowners argued
Senior Advocate R. Basant defended the High Court judgment. Section 17 was never invoked, he said. Both notifications contemplated a Section 5-A enquiry, nothing was tendered under Section 17(3-A), and the Board, not the Collector, took possession before any notification.
The Board and the Revenue Divisional Officer had admitted the lapse, and the 1999 awards passed after it were void.
The handover was not voluntary, since the consent was conditioned on payment under the Act. The owners had been out of their land for over three decades on Rs 60 per square yard, did not want alternative land, and sought compensation in accordance with law.
Two ways to take possession
The Court framed two questions. Did the acquisition lapse under Section 11-A, and with what consequence? And if so, should the direction for fresh acquisition be disturbed or the relief moulded?
On the first, Justice Kotiswar Singh began with the scheme of the Act. The State can take possession only after the award under Section 16, or in urgent cases under Section 17. The three-Judge Bench in R.L. Jain had held that possession taken before the Section 4(1) notification is outside the Act and title stays with the owner.
Section 17(1) needs a direction that the case is urgent, and the Collector may then take possession fifteen days after the Section 9(1) notice. Neither happened here. The Board, not the Collector, took possession before any notification, and nothing was tendered under Section 17(3-A).
Why Section 17 could not rescue the Board
Satendra Prasad Jain rests on the vesting that follows a valid use of the urgency power. In the ordinary case, land has not vested when no award is made within two years of the Section 6 declaration, and the proceedings lapse. This case fell squarely within that ordinary case.
The Section 17(2) argument failed too. That provision needs the previous sanction of the appropriate Government. The sub-station was a planned project decided on 7 January 1990, no sanction was ever given, and the Board took possession months before any notification.
“A letter of a Divisional Engineer cannot take the place of a statutory power that the Government never chose to invoke.” (para 19)
The Court read Lt. Governor of H.P. v. Avinash Sharma narrowly. Earlier possession was deemed Government possession there only because a Section 17(1) notification had been issued. Without it, nothing exists on which earlier possession can be grafted.
Delhi Airtech, a three-Judge Bench decision, held that even where Section 17(1) is invoked, missing the Section 17(3-A) deposit attracts Section 11-A. If lapse follows there, the Court said, it follows a fortiori where urgency was never invoked.
Consent, negotiation and delay
Paragraph 23 of Delhi Airtech saves vesting where the owner concedes the position. The Court found no concession here. The talks concerned only the amount, and were held on the footing of the consent letters, which preserved the owners’ rights under the Act. A later award cannot revive proceedings that lapsed by operation of law.
The “voluntary transfer” argument failed as well. The letter of 25 September 1990 sought only interim possession, the consent was conditioned on compensation under the Act, and no conveyance was ever executed. In Balakrishnan v. Union of India, by contrast, the full procedure had been followed and the owner settled only the amount.
On the admissions, the Court said its conclusion rested on the statutory scheme, not on any concession by the State, so B.S. Bajwa and Mahadeo v. Sovan Devi did not help. The owners’ right arose from the lapse, not from the letters of 1996.
On delay, Banda Development Authority involved owners who came to court nine years after the declaration, when third-party rights had arisen.
Here the owners moved court on 15 December 1997, within about two years of the Stage-II period ending, and no third-party rights intervened. The amounts they took were under protest, and “there can be no estoppel against a statute”.
What lapse means for title
The Court held that the proceedings lapsed under Section 11-A and the 1999 awards could not bind the owners. Once proceedings lapse, no proceeding remains under which the land could vest. The land vested neither under Section 16, as there was no valid award, nor under Section 17, which was never invoked.
As in R.L. Jain, the Board merely took possession and title stayed with the owners. They have been out of possession since 1990-91 and unpaid in accordance with law. On the options open, the bench said:
“either the land must be restored to its owners, or, if the State requires it for the public purpose, it must be acquired afresh in accordance with the law in force” (para 29)
Restoration did not commend itself. The Board had occupied the land for over three decades, and the sub-station serves, among others, the traction loads of the South Central Railway and the sub-stations supplying Tenali town. The owners had never sought the land back, and the High Court had not ordered the sub-station removed.
Why the relief was not moulded
The Corporation argued that fresh acquisition under the 2013 Act would cost about Rs 154.88 crore, by its affidavit of 16 October 2026. It asked that the owners be confined to rent, damages, alternative land or a lump sum.
The Court noted that fresh acquisition is what happened in R.L. Jain, where proceedings began anew to save the construction.
In Hemanagouda, possession was taken between 1968 and 1970 but acquisition began only on 2 February 1999. The direction also fits Article 300-A, which the Court read, through Kolkata Municipal Corporation v. Bimal Kumar Shah, to include a right of restitution or fair compensation and a right to an efficient and expeditious process.
“The moulding of relief is an equitable discretion of the Court, exercised to prevent an unjust result. It is not a right that a party in default may claim.” (para 33)
The Corporation’s cases did not help it. In Gauri Shankar Gaur, housing colonies had been built and sold to many buyers, and equity lay with them. Here no third-party interest arises. In Barangore Jute Factory, a highway stood on the land, and the Court moved the compensation date forward in the owners’ favour.
In Savitri Devi and NOIDA v. Ravindra Kumar, the challenges were late and large tracts had been allotted. Even so, the owners got a 64.7 percent enhancement and developed land in the first, and compensation under the 2013 Act in the second. Moulding here would only lower the payout.
Delhi Airtech distinguished on four grounds
Delhi Airtech had declined a fresh notification, reasoning that the compensation regime had changed so much that applying it to one owner would be unjust to the exchequer and other owners. The bench found it distinguishable on four grounds.
First, the appellant there held a small plot in a large planned layout, and other land-losers had settled under the old regime. Here the respondents are the only land-losers. Second, there the acquisition began under the Act with urgency invoked and the defect was a missing deposit. Here possession was taken wholly outside the Act.
Third, the award there came about six years after notification. Here more than three decades have passed, and freezing value at 1999 would give only about Rs 60 per square yard, a figure based on 1991 values. Fourth, Delhi Airtech itself said the “vice” of non-compliance by the acquiring authority cannot be converted into a “virtue”.
The conduct of both sides
The Court found no mala fides or negligence in the owners. They handed over land at the Board’s own request, took part in the enquiry and talks, never sought an interim order, and never asked for the land back.
The sham-sale allegation was not established: the doubted exemplars were executed by others, and the Anti-Corruption Bureau inquiry targeted public servants.
Their only lapses were procedural, namely the writ appeal dismissed for default in 2002 and restored in 2004, and legal representatives not brought on record in the High Court. Neither prejudiced the Corporation.
The Board stood differently. It took possession before any notification and deposited nothing for Stage-I. According to the Anti-Corruption Bureau report, its Executive Engineer asked on 31 January 1995 for the proposals to be republished in acres and cents because “the land cost may increase”.
The Board admitted the lapse in January 1996 yet caused no fresh notification for three decades. The Court did not find mala fides, but called it a sustained default. Moulding relief to fix an earlier value would reward the party in default.
The Rs 154 crore objection
The burden on the exchequer, the Court said, is the direct result of the authority’s failure to acquire or pay for the land for over three decades.
There was also no material to fix a fair figure. The Rs 154 crore is an estimate with no valuation behind it, and any sum set by the Court would be little more than a guesstimate.
The owners, who had reserved their right to compensation under protest since 5 October 1990, sought only compensation in accordance with law. While Rs 154 crore is a huge sum, the Court said, it does not shock the conscience so as to warrant intervention. The 2013 Act machinery is the right forum.
The alternative land offered, Ac. 7.14 near Tenali, belongs to private individuals, and the owners cannot be compelled to accept it. The lump sum of Rs 47,72,32,560 offered on 3 November 2026 freezes value at 1 January 2014 and deducts the awards with interest. The owners never accepted it.
The High Court, the bench concluded, struck the right balance. The sub-station is preserved, and the owners receive compensation in accordance with law.
Order
The Court dismissed the appeals, with no order as to costs. It upheld the High Court judgment of 19 April 2018 in Writ Appeal No. 2163 of 1998 and the consequential judgments in L.A.A.S. No. 1610 of 2005 and L.A.A.S. No. 444 of 2007. The interim order of 3 July 2019 stands vacated.
The High Court’s three-month period expired while its judgment was stayed at the Corporation’s instance. The Court therefore directed that fresh acquisition proceedings be initiated within three months, with compensation determined and paid as expeditiously as possible under the law in force. Pending applications stand disposed of.