State silence in written statement does not waive Section 80 notice, rules Bombay HC
An advertising firm sued Maharashtra for Rs 1.28 crore over a cancelled highway beautification contract without serving the mandatory two-month pre-suit notice. Justices G.S. Kulkarni and Neela Gokhale upheld dismissal of the suit, holding the statutory threshold cannot be waived by mere omission.
The Bombay High Court has affirmed the dismissal of a Rs 1.28 crore damages suit brought by an advertising firm against the State of Maharashtra, ruling that the government’s failure to object in its written statement does not waive the mandatory pre-suit notice under Section 80 of the Code of Civil Procedure, 1908.
In a judgment pronounced on 27 November 2026, Justices G.S. Kulkarni and Neela Gokhale held that Section 80(1) places an independent duty on civil courts to verify compliance at the threshold of institution.
Only an express waiver at the time of filing, or prior leave of the court for urgent relief under Section 80(2), can excuse a plaintiff from serving the two-month notice on the State.
A flyover beautification contract that unravelled
The dispute began with a proposal by M/s. Harsh Advertising to beautify and maintain the centre median verge of the Andheri flyover along the Western Express Highway, awarded through the Assistant Engineer-I, Road Development Sub Division No. 10. On 17 December 2015, the authorities accepted the firm’s offer and sought an undertaking on a Rs 100 stamp paper.
The firm stated that on 13 February 2016 it was asked to begin work because the Prime Minister was scheduled to visit Mumbai in late January or early February 2016. On 2 February 2016, the firm submitted its undertaking alongside a Rs 50,000 security deposit and Rs 1,38,000 as first-year rent.
On 30 March 2016, the State sent a revised contract cutting the allotted pole kiosks to one-third and raising the space reserved for social messages from 10 per cent to 25 per cent without assigning reasons.
After discussions, the firm accepted substitute sites below the Andheri and Vile Parle flyovers and outside Airport Colony, which it said held far less commercial value, and deposited a further Rs 90,000 in rent.
Then, on 13 June 2016, the authorities cancelled the permission with immediate effect and directed the firm to remove its billboards within eight days. The firm filed Commercial Suit No. 164 of 2016 before the High Court, seeking to quash the cancellation, restore its goods, restrain third-party rights, or recover Rs 1,28,28,000 with 18 per cent annual interest.
Trial dismissal and the waiver argument on appeal
After the pecuniary jurisdiction of the City Civil Court was enhanced, the suit was transferred to the City Civil Court at Mazgaon. The State filed its written statement contesting the claim, and the trial judge framed issues on maintainability under Section 80 CPC alongside merits issues on work completion and termination.
On 4 April 2026, the City Civil Court answered the threshold issue in the affirmative, held the suit bad for want of a Section 80 notice, marked the remaining merits issues redundant, and dismissed the suit. No one appeared for the State respondents when the High Court heard the commercial first appeal.
Advocate Abhishek Sawant, appearing with Shrey Fatterpekar, Ameet Mehta, Nirav Marjadi, Sanil Gada, Kushal Harnesha, and Ashraf Shaikh for the appellant, raised a single narrow ground. Because the State had not pleaded non-compliance with Section 80 in its written statement, he argued, the defendants had waived notice and the trial judge ought to have decided the suit on merits.
In support, counsel cited the Madhya Pradesh High Court ruling in Managing Director Corporation Lamta Project Balaghat v. Bhejanlal (2023).
Why Section 80 binds the court at threshold
Authoring the judgment for the division bench, Justice Kulkarni examined Section 80(1) and Section 80(2) CPC alongside nearly a century of precedent. Under Section 80(1), no suit may be instituted against the Government until two months after written notice stating the cause of action, plaintiff’s details, and relief is delivered.
Section 80(2), inserted by the 1976 amendment, permits a suit for urgent or immediate relief without prior notice only with the leave of the court, and bars any relief until the Government receives a reasonable opportunity to show cause.
In paragraph 13, quoting the Privy Council in Bhagchand Dagdusa Gujrathi v. Secretary of State for India (1927), the bench recalled the strict statutory bar:
“Section 80 is express, explicit and mandatory, and it admits of no implications or exceptions.”
Tracing the rule through Sawai Singhai Nirmal Chand v. Union of India (1966) and State of A.P. v. Pioneer Builders (2006), the bench reaffirmed that Section 80 imposes an unqualified duty upon the court.
Under Pioneer Builders, prior leave under Section 80(2) is a condition precedent that must precede institution of a suit without notice, with recorded reasons showing application of mind.
In paragraph 16, the Court explained why silence in the State’s written statement could not cure the omission:
“Such defect goes to the root of the institution, and it is such obligation which is cast on the Court in examining whether such mandatory compliance of the provisions of law has been adhered by the Plaintiff.”
Applying that test, the bench noted that Harsh Advertising had admittedly neither served a Section 80(1) notice nor obtained prior court leave under Section 80(2) for urgent relief. Mere silence in the State’s written statement could not cure a defect going to the root of the suit’s institution.
The bench added that only an express waiver at the time of institution could dispense with Section 80, and distinguished the Madhya Pradesh High Court’s single-judge decision in Lamta Project as taking no view different from Pioneer Builders.
Order
On 27 November 2026, the Bombay High Court dismissed Commercial First Appeal No. 25 of 2026 and upheld the City Civil Court’s judgment dated 4 April 2026 dismissing the suit, with no order as to costs.