Calcutta High Court sets aside award passed behind 12 companies; arbitrator destroyed the file
Justice Shampa Sarkar held that no signed copy of the 2017 award reached the companies, so the Section 34 clock never started, and that the award could not survive without the arbitral record.
The Calcutta High Court has set aside an arbitral award that was made behind the backs of twelve companies, on a sale agreement they say they never signed. Justice Shampa Sarkar delivered the judgment on 25 November on the Original Side.
The award dated 16 October 2017 had been passed by a sole arbitrator. When the court asked for the arbitral record, he wrote that he had destroyed it. The claimant and the other respondents could not produce the pleadings the award rested on.
Twelve companies and one Madurdaha plot
The application, AP No. 491 of 2021, was filed by Leonine Estates Pvt. Ltd. and eleven other companies under Section 34 of the Arbitration and Conciliation Act, 1996. It sought to set aside an award in ARB Case No. RT/006 of 2017, passed by the named arbitrator Mr Dipak Chakraborty, an advocate.
The claimant before him was Ritman Infra Limited, now respondent no. 1. It had invoked the arbitration clause in a sale agreement dated 8 December 2014. Clause 7 provided that failure to perform the covenants would be settled by arbitration, with Mr Chakraborty as sole arbitrator.
The land is premises No. 736 Madurdaha, Kolkata, about 128 cottahs 12 chittacks and 33 square feet in Mouza Madurdaha. According to the companies, it was bought through 14 deeds of conveyance. Each of the petitioners and respondent nos. 2 to 7 held a one-eighteenth share.
How the companies learnt of the award
The companies filed Title Suit No. 818 of 2018 for partition of the same premises, in the court of the Civil Judge, Senior Division, 4th Court at Alipore. In a related miscellaneous appeal, the District Judge ordered the parties to maintain status quo on the property, and that order was continued.
Mr Ghanshyam Das Sharma, known as G.D. Sharma, then filed an application under Order 7 Rule 11 of the Code of Civil Procedure for rejection of the plaint. He filed it on behalf of respondent nos. 2 to 7.
A copy was served on the companies’ advocate on 23 March 2021. It annexed a photocopy of the award and of the unregistered sale agreement. The companies say that is how they first came to know of both. They filed the Section 34 application on 26 November 2021.
The companies’ case: fraud and no hearing
Mr Debnath Ghosh, Senior Advocate, with Mr Sarosij Dasgupta, Mr Aditya Mondal, Ms Shomrita Das and Mr Shomrik Das, appeared for the companies. He argued that the award gave no reasons and was the product of fraud. The arbitrator, he said, was not impartial, and no notice of arbitration was served.
The companies denied signing the agreement. Mr Sharma, who signed for them, had no authority, Mr Ghosh argued. The board resolution he relied on had been fraudulently obtained. The award rested on admissions in a written statement the companies say they never filed.
The timeline mattered to that argument. Mr Sharma was a director of the companies until 11 August 2017, when a resolution removed him. Forms DIR 12 recorded the removal. The registered office moved to a suite at Chatterjee International Centre with effect from 1 August 2017, and Forms INC 22 were filed.
Respondent no. 1 was owned and controlled by one Parag Majumdar, the companies said, and respondent nos. 2 to 7 by Mr Sharma. They called the arrangement a collusion between the two men. They pointed to other details too.
The email address in the agreement belonged to Mr Sharma’s son. The award gave the companies’ address as 3 Dr Rajendra Road, Bhawanipore, which was Mr Sharma’s residence.
Counsel added that a letter from the claimant on 17 July 2017, demanding execution of the agreement, went to the old registered office. By a letter of 3 August 2017 the companies replied that they knew of no such agreement and asked for a copy.
The claimant’s answer
Mr Rajarshi Dutta and Mr Abheshek Sikdar appeared for the claimant, and Mr Bhaskar Roy for respondent nos. 2 to 7. The claimant said the agreement was real. It said possession was handed over when the agreement was signed, and that it had paid Rs 55,31,808 as advance.
The claimant said it had managed the premises, paid the security guards’ bills and supervised the site since then.
It cited a letter of August 2015 from one Jitendra Kumar Thirani, written after an advertisement the claimant published in the newspaper Aaj Kaal. The letter said that Rajesh Agarwala, also called Jalan, claimed a 40 per cent stake in the 17-company project at the site on behalf of Leonine.
The claimant also relied on its 17 July 2017 letter to argue that the companies knew of the agreement. The allegation that they had no knowledge of it, it said, was false.
On procedure, it said the arbitrator wrote on 15 September 2017 that he had entered upon the reference. He passed the award on 16 October 2017 and communicated it by letter the same day to every party. Newspaper notices were also published, it said.
The respondents also pointed to Beniapukur Police Station Case No. 462 of 2017, which Mr Sharma lodged against Arun Kumar Mohta and Rajshri Mohta over his removal. The police charge-sheeted them. In their account, that undercut the claim that Mr Sharma acted against the companies after he was removed.
They argued the application was hopelessly barred by limitation. They also said it had been filed in the wrong division, because the dispute was a commercial dispute under the Commercial Courts Act, 2015.
Limitation never began to run
The court started with limitation. Section 31(5) of the Act requires a signed copy of the award to be delivered to each party. The judge found that neither the respondents nor the arbitrator could show that this was done for the companies.
The arbitrator had also been told to produce the record and had not. The letter the respondents relied on was addressed to the companies through Mr Sharma, at his residential address. By then he had been removed as director and the registered office had moved.
“Even if it is assumed that the award was sent to G.D. Sharma, that was not sufficient compliance of Section 31(5) of the Arbitration and Conciliation Act 1996.” (para 23)
Limitation under Section 34(3) therefore did not start. The companies learnt of the award on 23 March 2021 and filed on 26 November 2021. The court added that the Supreme Court, in Cognizance for Extension of Limitation, In Re (2022) 3 SCC 117, had excluded 15 March 2020 to 28 February 2022 from limitation periods, including under the Act.
The court relied on Motilal Agarwala v. State of West Bengal (2025 INSC 1062) and State of Maharashtra v. ARK Builders Pvt. Ltd. ((2011) 4 SCC 616). It reproduced long passages from both.
In Motilal Agarwala, the Supreme Court held that a party under Section 2(1)(h) is a party to the arbitration agreement. Delivery to an authorised representative was not delivery on the party. The passage notes that delivering the award is a matter of substance, not a formality, because several limitation periods run from it.
ARK Builders held that the Section 34(3) period runs only from delivery of a duly signed copy to the party. A copy supplied by the claimant did not change that. The passage adds that the law should not be tailored to the facts of a case.
The court distinguished two cases the respondents cited. In Union of India v. Bhola Prasad Agarwal (2022 SCC OnLine Chh 1644), the award debtor had not raised non-service in its Section 34 application. It also knew of the compensation proceedings that used the award.
Anilkumar Jinabhai Patel v. Pravinchandra Jinabhai Patel ((2018) 15 SCC 178) accepted service on the head of a family or a power-of-attorney holder representing a party. The judge said the facts here were completely contrary to that.
A land sale is not a commercial dispute
The second objection was jurisdiction. The Commercial Courts Act, 2015 covers agreements relating to immovable property used exclusively in trade or commerce under Section 2(1)(c)(vii). The court held that the sale agreement did not fall within that clause.
The schedule described the property as land with a tin shed and a darwan’s room of about 1,000 square feet. Mr Sharma’s own affidavit-in-opposition described it the same way, as land with a tin shed.
The court quoted Ambalal Sarabhai Enterprises Ltd. v. Infraspace LLP ((2020) 15 SCC 585). On the quoted passage, the word used in the clause means actually used, not ready for use or likely to be used. Property merely likely to be put to trade use does not bring a dispute within the clause.
The land here was primarily vacant, the judge said. The agreement was not a development agreement to exploit the property commercially. It was a sale of land with payments to be made in stages as construction was raised.
The respondents had pointed to the sale agreement’s reference to an earlier development agreement. The court held that the agreement before it was not itself a development agreement with the owners.
A Division Bench ruling, Kedarnath Tradecomm LLP v. Mayank Agarwal (APO No. 41 of 2024), did not help them. The court noted that the parties there had accepted that the dispute was commercial.
No notice, no pleadings, no record
On the merits, the court found no evidence that the companies ever received a Section 21 notice invoking arbitration. Respondent no. 1, it said, had not satisfied the court that the arbitration clause was validly invoked.
Nothing showed that the companies knew of the statement of claim or were served with it. Mr Sharma had left the boards, and Forms DIR 12 evidenced it. The respondents themselves admitted the removal. Every communication from the arbitrator went to Mr Sharma at his home address.
The court also found nothing on record to show his authority to represent the companies.
The court then asked for the statement of claim and the written statement of defence, on whose admissions the award had been passed under Order 12 Rule 6 of the Code of Civil Procedure. Nobody could produce them.
Mr Sharma had affirmed the respondents’ affidavit but did not file the arbitral pleadings when asked. Mr Dutta sought time to file a compilation and did not do so. The arbitrator was asked for his records on 5 August, 26 August and 17 September 2025.
He wrote to the Registrar, Original Side, on 11 September 2025. The letter says the arbitration was more than eight years old and that he had destroyed all the arbitral proceedings, which were no longer in his office. The judgment reproduces the letter in full.
That left the court with no arbitral record, no statement of claim and no written statement. It held that an adverse presumption could be drawn against the parties who should have held those documents and withheld them. The arbitrator had also produced nothing to show the award was ever served.
Fundamental policy and natural justice
On this footing, the judge held that the companies had established they knew of neither the arbitral proceeding nor the award.
“The award was passed behind their back and they were not heard.” (para 41)
The court held that the proceeding was vitiated by procedural defect and by non-compliance with the fundamental policy of Indian law. Proper service on all parties had not been made, and the parties were not allowed to contest as the law prescribes. The award was passed in violation of natural justice.
The agreement for sale was unregistered and insufficiently stamped, the judge added, which made the award contrary to Indian law. Mr Sharma’s purported admission did not bind the companies. The written statement containing it had never been produced.
The court concluded that the making of the award was induced and affected by fraud. It was passed in violation of the fundamental policy of Indian law, at the instance of a party not authorised to represent the companies or to file a defence for them.
Mr Ghosh had argued that breach of natural justice made the award contrary to the fundamental policy of Indian law, and the court accepted that reading on these facts.
The judgment sets out the Supreme Court authorities on that policy. These are ONGC Ltd. v. Western Geco International Ltd. ((2014) 9 SCC 263), Associate Builders v. Delhi Development Authority ((2015) 3 SCC 49) and Ssangyong Engineering and Construction Company Ltd. v. NHAI ((2019) 15 SCC 131).
The passages reproduced include the duty to adopt a judicial approach and to follow natural justice. They also cover the equal treatment and full opportunity guaranteed by Section 18 of the Act and the improper-notice ground under Section 34(2)(a)(iii).
Those authorities also describe the other recognised grounds. They include an award contrary to the interest of India, to justice or morality, or patently illegal. Illegality, they say, must go to the root of the matter, and a trivial defect is not enough.
The judge applied the fundamental-policy ground to the missing notice, the missing hearing and the missing record.
Order
The award dated 16 October 2017 in ARB Case No. RT/006 of 2017 is set aside. AP No. 491 of 2021 is allowed and disposed of.
The judgment was reserved on 10 September 2026 and pronounced on 25 November. It does not decide title to the Madurdaha land, and no order on costs is recorded. Urgent certified copies may be supplied to the parties on completion of formalities.