Uttarakhand HC: PMGSY contractor to get Rs 50.78 lakh in four weeks, Rs 52.68 lakh to committee
The department told the court it would pay the admitted part of a Rs 1.03 crore bill and said the road was built on a changed alignment, leaving 675 metres. The firm agreed to take the rest to the contract Dispute Redressal Committee.
A firm that built a Pradhan Mantri Gram Sadak Yojana road asked the Uttarakhand High Court to make the department pay about Rs 1.03 crore. On 18 November the court split the claim in two. The admitted Rs 50.78 lakh is to be paid in four weeks, and the other Rs 52.68 lakh goes to a contractual committee.
Justice Pankaj Purohit disposed of the writ petition after the department and the firm each accepted the arrangement.
The road and the bill
Rama Gupta Constructions did the balance work on the Purkul Village to Bhitarwali-Kimari Motor Road. It had already been to the High Court once, in WPMS No. 3526 of 2025, which ended in an order of 19 December 2025.
The firm said that order had not been complied with. It filed a Variation Final Bill on 1 January 2026 and asked the court to direct payment of all pending dues, after only lawful statutory or contractual deductions.
Six reliefs, one figure
The petition named the State, the Pradhan Mantri Gram Sadak Yojana, the Chief Engineer of the Uttarakhand Rural Roads Development Agency and an Executive Engineer. It sought a mandamus to release the amount shown as payable in the 6th Running or Variation Final Bill, including Rs 1,03,47,321.75 with GST.
In the alternative it sought the admitted or undisputed amount at once. It also asked for a speaking, item-wise and measurement-wise order on any deduction the department proposed.
The firm further claimed interest at 18 per cent a year from the date the work was completed until payment, and the costs of the petition.
What the department said
The court had called for the department’s instructions. The department said it was ready to release Rs 50.78 lakh with GST, and that the remaining Rs 52.68 lakh was disputed.
Counsel for the department added that the road was built after its alignment was changed, which left a stretch of 675 metres. For the disputed sum it said the firm could go to the Dispute Redressal Committee under Clause 24.2 of the contract.
The firm takes the committee route
The petitioner’s counsel asked for time to take instructions on that proposal. On 18 November he said the firm was ready to raise the dispute over the Rs 52.68 lakh before the committee, together with the other requisite amounts deposited by the firm.
Mr Sagar Kothari appeared for the petitioner and Mr Devendra Singh Bohra, Deputy Advocate General, for the State.
Four weeks to pay, six months to decide
Justice Purohit disposed of the petition and gave the firm liberty to raise the dispute before the committee as it had stated. If the claim is raised, the committee must decide it at the earliest and no later than six months from the date the dispute is raised.
The court also made it clear that the Rs 50.78 lakh with GST, which the department admitted, must be released to the firm within four weeks from 18 November.
Order
The writ petition is disposed of. The firm may raise the Rs 52.68 lakh dispute before the Dispute Redressal Committee under Clause 24.2 of the contract, which has six months from that date to decide it.
The department pays Rs 50.78 lakh with GST within four weeks of 18 November. Pending applications stand disposed of. The order does not mention the claim for interest or costs.